Project Schedule for Longwood Public Works Department

Sidewalk Repair Projects

Sleepy Hollow

Starting in November 2009.  Work expected to take approximately 2 weeks.

Skylark Subdivision

Starting in January 2010.

Columbus Harbor

Upon completion of Skylark work.

Tiberon

Upon completion of Columbus Harbor work.

Signage, Potholes, and Tree Trimming

The Public Works department will repairing and replacing signage, repairing potholes, and trimming trees throughout the City as needed.

Stormwater

404 E. Palmetto

Trench drain installation project beginning December 7, 2009 and lasting approximately 3-4 days.

Arts & Crafts Festival

Barricades will be set up for road closure associated with festival on November 20, 2009.